BUILD PROGRAMME/ TIMELINE





                    Planning Application                       Planning Application                        On-site Construction                            Construction
                        Submitted                                    Granted                                      Starts                                   Completion

                           June                                      October                                     January                                    September
                          2024                                        2024                                        2025                                        2025